Dear Property Owners,
This letter is to report on several issues the LMRPOA Board is
addressing. We have obtained a complete insurance package for the coming year,
including directors and officer’s liability insurance. As explained in my
earlier letter, our 2004 D & O insurer refused to renew our policy due to the
costs they incurred in the last few years responding to owner’s lawsuit threats
about trails and roads. Despite this, our insurance costs for the year are only
$800 over budget and $1600 higher than in 2004, although the D&O insurance now
has a $1000 deductible.
At the recommendation of the attorney retained by the insurance
company to respond to the threatened lawsuit concerning road conditions, we
commissioned a study by a civil engineering firm to recommend maintenance and
improvements to ensure that the community’s roads are safe and economically
viable. This study cost $3600.
A copy of the engineering study is enclosed. It recommends near
term signage and drainage improvements and lists longer term improvements
including adding base material and widening the roads to 18 feet in the few
places that our roads are narrower. Speed limit signs at 15 mph are recommended
as well as signs to yield at the one-way bridges and warning signs for sharp
turns.
As far as paving the roads, the report states that based on our
low traffic volumes it would appear more cost effective to maintain the gravel
roadways than to pave them. If we choose to pave the roads, the report
recommends modifying the roadway profiles (cutting down hills) to conform with
higher speeds on the roads, and designing each roadway to be in accordance with
the Yavapai County design guidelines for community roads. In addition to
modifying profiles, this would require widening roads and placing six inches of
base materials on all roads. This Board will only consider paving the community
roads when a majority of the parcel owners are in favor of paving.
The Board believes that the signage and drainage recommendations
in the engineering report should be implemented soon. We estimate these will
cost about $34,000 or $515 per lot. If completed this year, a special
assessment will be required.
The Board also thinks that additional base material should be
placed on the roads. We have sent out a RFQ asking for bids to place three
inches of additional material on all roads. Only two bids have been received,
both from large construction firms. The lowest bid was $373,000. This bid is
roughly twice the cost of the lowest bid received last year. These bids are
higher due to increased material and fuel costs as well as the many other
construction projects in the county that are keeping contractors busy. It is
quite possible that if we spread out the base improvement work over a longer
period we could get smaller contractors to bid at a lower cost and could
schedule work during periods when fewer other projects are underway.
Several possibilities exist for phasing the base improvement work
including:
·
Place three inches of material this year at
$373,000 or $5651 per lot
·
Phase the placement of additional material over
several years with the possibility of lower overall costs
If the project is conducted over several years it could either be
funded with a series of special assessments, or the dues could be increased to
cover the expense.
To implement these improvements may require a special
assessment. Our lawyer has informed us that our current CC&R’s do not allow the
owners to vote to approve a special assessment. They tell us that only the Board
can make such decisions. You were recently asked to approve a CC&R change that
would have given this responsibility to the property owners, but the vote was 34
FOR and 22 AGAINST, less than the 50 votes needed to approve the change.
Nonetheless, this Board is committed to obtaining your views on
how this work should be phased over time, and if it should be done by special
assessment or built into the dues structure. A survey card is enclosed
soliciting your views on these projects and their phasing. Please return the
survey before June 15, 2005.
We understand that you will probably find the cost of this work
surprising, given that you were asked last fall by the previous Board to approve
a $6800 special assessment to chip seal all the roads. The cost of this
previous proposal was unrealistically low because it did not include any
drainage or base material improvements. Similar projects have been done in
nearby communities, and the surfaces have already failed in many locations. The
Board estimates that the costs for preparing the community’s roads and placing a
hard surface following the recommendations in the engineering report will exceed
$20,000 per lot.
Please keep in mind that the community roads are currently in
much better condition than they were when our lots were first sold. LMRPOA has
spent approximately $2,000 per mile per year for 9 years to maintain and improve
these roads. The work proposed here will result in significant improvements
over the current road conditions.
Finally, Scott Robertson has resigned from the Board. At the
June meeting a replacement for Scott, whose term runs until October 2006, will
be elected. Anyone interested in applying for this position should contact me.
Sincerely,
Neil Cooperrider
President, LMRPOA
(928) 899-3321,
neil@cooperrider.org
Attachments:
Shephard-Wesnitzer
Roads Study - PDF
Member Survey - PDF